The replacement of the large DN 500 mm pipeline in Ambohimiandra was completed yesterday morning. The work, scheduled for three days, was finished according to the set timeline, despite technical constraints encountered on site. Indeed, another damage was detected on a DN 250 mm pipeline during the intervention. To prevent the situation from worsening and avoid repeated disruptions, Jirama decided to immediately undertake the necessary repairs. This intervention affected Mandroseza, Ambohimiandra, Ambohidraserika, Ambatoroka, Ambanidia, Ankorahotra, Ankazotokana and Anjohy. All work was completed yesterday, but Jirama technicians continue close monitoring of the new infrastructure to ensure its stability and proper functioning. According to explanations, water supply was gradually restored yesterday, depending on network filling. The districts of Ankadifotsy, Manjakaray, Soavimbahoaka, Nanisana, Ampasampito, Ankadindramamy, Ankerana, Analamahitsy, Ivandry, Soavimasoandro, Ambatobe, Masinandrina, Ambohitrarahaba, Ankadikely, Ilafy and surrounding areas are affected by this gradual return to normal.